All projects
Manufacturing

Capacity and scaling programme for a manufacturer

The constraint wasn't the machines. It was the changeover.

An export contract on the table would have roughly doubled output requirements. The board's instinct was capital expenditure — a second line, financed. Before signing anything, we measured where capacity was actually going. Most of the shortfall was changeover time and unplanned downtime, neither of which a new line would have fixed.

Industrial production line — manufacturing operations and capacity planning
Client
Industrial manufacturer, export contracts
Engagement
20-week scaling programme
Market
Punjab, Pakistan
Delivered
2024–2025
The situation

What we walked into

  • An export contract requiring close to double the current output.
  • A capital plan for a second line, financed, with payback resting on optimistic uptime.
  • No reliable measure of where production hours were actually being lost.
  • Quality rejections handled reactively, with rework absorbing capacity nobody had counted.
The approach

What we actually did

01

Measure before spending

Four weeks of structured observation and machine logging to establish true overall equipment effectiveness. Changeover and unplanned downtime accounted for the large majority of lost capacity — the line itself was rarely the binding constraint.

02

Attack changeover first

Structured changeover reduction — preparation moved off-line, tooling standardised, and the sequence rehearsed — recovered a substantial share of the needed capacity for a fraction of the capital cost.

03

Make quality preventive

In-process checks moved upstream to where defects originate, with rework tracked as lost capacity rather than written off as a cost of doing business.

04

Instrument the floor

Our engineering team built a simple production dashboard — output, downtime reason codes, and rejection rates visible to supervisors in real time instead of reconstructed at month end.

The result

What changed

+34%
Effective capacity, existing line
-58%
Average changeover time
Deferred
Second-line capital expenditure
-3.1pts
Rejection rate
  • The export contract accepted and served from the existing plant.
  • A major capital commitment deferred rather than financed on optimistic assumptions.
  • Downtime reasons recorded and acted on daily rather than debated quarterly.
  • Quality treated as a capacity issue, which is what it had always been.

Client identity is withheld under confidentiality. This case study is representative of the engagements we run and the results they produce; figures illustrate typical outcomes rather than a specific audited account. We're happy to discuss specifics, and arrange references, on a call.

Ready when you are

Let's build the next chapter of your business — together.

Tell us where you are and where you want to go. We'll come prepared.